|
Project
Examples
Project
Examples
Animas
River near Aztec, NM
Severe
bank erosion at a meander bend of the river had taken approximately
2.5 acres of horse pasture (alluvial terrace) and washed it downstream.
Left unchecked, this lateral extension of the river would eventually
lead to a meander bend cutoff, causing loss of land, a large sediment
load downstream, and base lowering of the river by 10 plus feet
(wide spread geomorphic repercussions). The private landowner had
tried building an earthen dike to divert the river away from the
erosional area, but after a few years the river had washed away
most of the dike. Large scale riprap was contemplated to prevent
further land loss. When the landowner contacted the New Mexico Environment
Department to seek funding assistance under the EPA's 319 program,
NMED suggested that a Natural Channel design approach be considered
instead.
Riverbend
Engineering was retained to assess the river and to propose a stable
river channel solution using Natural Channel Design techniques.
Analysis of historic aerial photography revealed the progression
of meander bend extension through time, and the relatively recent
rapid erosion problem. At this particular location the river had
developed a radius of curvature smaller than any other location
for 5 plus miles up and downstream. It was clear that a meander
bend cutoff sequence had begun, and needed to be mitigated as soon
as possible. NMED's criteria for funding assistance included mitigation
of in-stream deposits, so the design solution had to be hydraulically
effective. After performing a detailed topographic survey of the
site, and a geomorphic assessment of the rivers condition, Riverbend
Engineering selected a solution based on a sustainable radius of
curvature and in-stream rock structures for channel stability.
The
design incorporated the reclamation of 1.5 acres of pastureland
at the terrace elevation, with another 1.5 acres of active floodplain
restored. Transplants of willows and Russian olive from on-site
sources were used to stabilize the reconstructed floodplain. In-stream
rock structures were built to prevent the floodwaters from eroding
the outside bank of the river, and these structures were keyed back
into the re-constructed floodplain with buried logs and old loader
tires salvaged on-site. The inside bank of the river bend was graded
to an appropriate point bar shape and elevation, allowing for high
flows to initially flood "river right". Constructed in the winter
months of 2003, this project has passed a peak flow during spring
runoff approximately 20% above bankfull discharge. Nature doesn't
seem to waste any time testing our restoration designs!
Riverbend
Engineering's contract includes monitoring of the project for several
years post-construction. Our as-built and post-flood surveys provide
a detailed evaluation of how the river is adapting to the imposed
form. After the first runoff season we observed fine grained sediment
deposition on the constructed floodplain, no floodplain erosion,
survival of 90% of the transplanted willows, stability of the constructed
banks, and minor sediment deposition along the channel margins above
the rock structures (as expected). The excavated pool structures
below each rock structure have adjusted the locations of maximum
depth and we will quantify how this changes over time with our monitoring
work. It is only through monitoring can the collective wisdom of
Natural Channel Design be implemented in environmentally effective
and cost conscious ways.
|